Project Charter: guide & examples

A project charter is a compact agreement about the problem, goal, scope, ownership and measures of an improvement project.

5 practical steps · 2 worked examples · Editable practice worksheet

Reading is free. Tool access requires a verified account; no manual beta approval or payment is required.

What is it, and why use it?

A project charter is a compact agreement about the problem, goal, scope, ownership and measures of an improvement project.

It makes the work accountable and gives the team a reference when priorities or assumptions change.

Explore the Project Charter features and local-file workflow

When to use it

Use it before committing time to a project or when an existing improvement has lost focus.

When another tool fits better

Use SMART Goals for several individual goals. Use A3 for a fuller evidence-based story as the investigation develops.

Before you start

  • Evidence of the present problem and who experiences it.
  • A sponsor, process owner and people who can contribute.
  • A baseline measure and a feasible review date.

Use fictional or approved non-sensitive information. Do not include patient details or proprietary records in practice worksheets.

Step-by-step in CI Tools

  1. Describe the Problem statement with a population, period and observed gap; do not start with a predetermined solution.

  2. Complete the goal and business case, explaining the benefit in terms the process owner understands.

  3. Define in-scope and out-of-scope work, roles, dates and the measures the team will review.

  4. Check the charter with stakeholders and resolve incompatible scope or goal statements.

  5. Save a local editable copy and revisit it when new evidence changes the project assumptions.

Separate a problem from a proposed solution

“Install a new system” is an action, not an observed problem. State the unwanted outcome, its frequency and its consequences, then test possible explanations before committing to an intervention.

Completed worked examples

Demonstrations only: all organizations, observations, targets and results below are fictional. They are not clinical instructions or universal performance standards.

Healthcare operations — fictional

Referral rework project

Starting information: A fictional service reviewed 100 referrals in April and found 30 needed missing information.

Completed demonstration: Referral rework project
Problem30 of 100 referrals required follow-up before scheduling
GoalReduce the rework rate from 30% to 15% by 30 September
ScopeReferral intake only; exclude clinical prioritization

What the result means: The charter names a measurable operational problem. The proposed target still needs feasibility review; it is not proof a specific form change will succeed.

General business — fictional

Invoice correction project

Starting information: A fictional distributor found 18 corrected invoices among 120 issued in a month.

Completed demonstration: Invoice correction project
Problem / baseline18/120 = 15% needed correction
GoalReach 8% or lower over the next three monthly reviews
OwnershipAccounts lead sponsors; billing team tests changes

What the result means: Use a consistent correction definition across reviews. Excluding inconvenient cases after the project starts would distort the baseline.

Practise in a separate worksheet

Open the tool’s built-in synthetic sample as a new editable worksheet. It may differ from the worked demonstrations above. It never replaces an existing worksheet. Save any work you want to retain to your computer.

Open built-in practice worksheet

You’ll be asked to log in if needed. No worksheet is created just by reading this page.

Common mistakes and how to avoid them

  • Embedding the answer in the problem: investigate before selecting a solution.
  • Writing an unlimited scope: state exclusions explicitly.
  • Choosing a deadline without ownership or baseline: agree all three together.

Interpret the result

A good charter makes decisions easier: does a proposed activity address this problem, serve this population and fit this scope? Revise assumptions transparently rather than moving the goal after seeing results.

Record the assumptions and unanswered questions alongside the result. Use the relevant local review process before making operational decisions.

Credible further learning

These independent educational resources explain the methods. They do not endorse CI Tools Suite. Some external resources have their own access requirements.

Resource links reviewed 29 October 2026. Our interface instructions and fictional examples are original CI Tools learning material.